In 2022 ANSA started the Cable Management project. The goal of this project was to organize and tidy up all data and electrical cables beneath the consoles in the ATC Tower Cabin, as well as the equipment racks in both technical rooms in the Tower building.
This project was executed in four phases:
- Installing new data cable patch panels and new network switches to accommodate CNS/ATM equipment.
- Transferring the existing data cable connections to the new patch panels and network switches.
- Retrieving old data and electrical cables from beneath the Tower console and the equipment racks in both technical rooms, as well as tidying up the remaining data and electrical cables.
- Organizing and installing new electrical power outlets beneath the Tower console.
This project has been successfully completed on January 31st, 2023. We would like to thank our CNS/ATM Systems Team for their good work.